SUMMER 2018 WORKS BRIEFING update 2

Thorneycreek drive bridge

Strengthening works have been completed and the bridge is open.  The car park remains CLOSED.

2 Sylvester Road

This project has been ongoing since mid-March – thank you for your patience and cooperation.  Building works are expected to be completed by mid-July with furniture fitting then ongoing to mid-August.  The house will be ready for student occupation to coincide with the start of Graduate arrivals 22 September 2018.

One tree on the boundary between 2 Sylvester and 1A Sylvester will be removed during w/c 13 August.

Thorneycreek Cottage

Compound remains a restricted area.

This project involves major repairs and renovations including the removal of the roof, clearance of internal structures and under-pinning work.  The rebuild of the house is expected to take at least 9 months (March 2019) and may take longer.

Thorneycreek House

The work at the Cottage will affect access to/from the House.  There will be directed routes which are shown on the plan.  Please restrict yourself to these routes.

Main College Building Refurbishments

Flat 8 and Sets 28 and 31 will be refurbished this summer as well as 5 bathrooms (TBC).  Work is ongoing.

Power outage 22nd August

As part of the continuing installation of the Heat Exchange Unit in Bin Brook, connection of supplies will be undertaken on Wednesday 22nd August from 9.00am until 5.00pm.

Heat, light and power isolations will affect the Main College Building, 1 Sylvester Road, 1ASylvester Road, 4 Adams Road, CWB.

IT network, internet, etc will be affected in all parts of College from 8.45am until 5.30pm (or 30 minutes after power is restored).

Tree Surgeon works

Various areas will be affected for short periods while tree works are undertaken during w/c 13 August.  Affected areas – Herschel Rd boundary, 1A/2 Sylvester Rd, bottom of Thorney Creek lawn, 3 Sylvester Rd, Wardens Lodge.  Please observe restrictions and signage.

Pond fountain

Installation of a new fountain in the pond will be undertaken during September.  This will involve the partial emptying of the lake and some digging work.

6 Adams Road

The paths around the house will be relaid during the summer vacation.  The work will involve limited excavations and there will be restricted access in place throughout the period.

2 Adams Road cycle shelters

New cycle shelters will be installed on the eastern side of the house during the summer vacation.  The work will involve limited excavations and there will be restricted access in place throughout the period.

2 Adams Road

It is anticipated though still subject to confirmation, that a programme of window replacements will commence this summer.  There will be limited disruption in those rooms affected as windows are removed and replaced.  Further advice will be given as plans are confirmed.

Correct as at 14 August 2018