The Estates team are making improvements to our electrical infrastructure. Thank you for your patience whilst we isolate local areas of the building for short periods.
| Date & Time | Areas/Services Affected |
|---|---|
| Mon 27 Jul, 07:00–10:30 | Q Lift will be unavailable. Please use K Lift or the staircases during this period. |
| Mon 27 Jul, 11:00–14:30 | K Lift will be unavailable. Please use Q Lift or the staircases during this period. |
| Mon 27 Jul, 15:00–18:00 | Air conditioning and cooling systems serving parts of the building, including plantrooms and associated comfort cooling equipment. |
| Tue 28 Jul, 07:00–11:00 | Workshop cooling and ventilation systems, together with associated maintenance-area mechanical services. |
| Tue 28 Jul, 11:30–15:00 | Kitchen and catering power supplies. Some catering equipment may be unavailable during this period. |
| Tue 28 Jul, 15:00–18:00 | Maintenance workshop, maintenance offices and adjacent corridor power and lighting services. |
| Wed 29 Jul, 07:00–10:30 | Communications room sockets, switch room sockets, corridor lighting, wine cellar lighting and associated control systems. |
| Wed 29 Jul, 11:00–14:30 | Basement services, car park-related systems and associated plant controls. |
| Wed 29 Jul, 15:00–18:00 | Underground car park systems, storage cage controls and associated ventilation/control equipment. |
| Thu 30 Jul, 07:00–10:30 | Fire alarm system power supply. Temporary fire safety arrangements will be in place during the works. |
| Thu 30 Jul, 11:00–14:30 | IT and communications infrastructure, including network cabinets, communications room power supplies and associated cooling systems. |
| Thu 30 Jul, 15:00–18:00 | Basement plantroom services and equipment serving the auditorium and surrounding building services. |
| Fri 31 Jul, 07:00–11:00 | Auditorium and theatre-related power and support services. |
| Fri 31 Jul, 11:30–15:30 | Stage lighting systems, dimmer equipment and associated theatre lighting services. |
| Fri 31 Jul, 15:30–18:00 | Reserved contingency period for testing, remedial works or any necessary follow-up activities. |
| Mon 03 Aug, 07:00–10:30 | H Staircase lighting, power and emergency lighting systems. |
| Mon 03 Aug, 11:00–14:30 | Porters' Lodge, Library, Teaching Rooms 1–7, Laundry facilities and Chapel lighting controls. |
| Mon 03 Aug, 15:00–18:00 | Roof-level and upper plantroom services, including associated building plant equipment. |
| Tue 04 Aug, 07:00–10:30 | Plant services supporting roof-level and auditorium-related building systems. |
| Tue 04 Aug, 10:45–14:15 | Final transfer works affecting remaining plant services and associated support systems. |
| Tue 04 Aug, 14:30–18:00 | Reserved contingency period for testing, remedial works or any necessary follow-up activities. |