Archives Building - Progress Report week 15

26 September 2019

Bill McKim Facilities Manager

  • Roof plate completed
  • 1st Floor screed complete
  • Blockwork to gable ends complete
  • Roofing trusses complete
  • Front brick elevation and rebated slips complete

To see the latest drone footage, click here.

Wire ties and steel reinforcements for 1st floor screed

Screed to 1st floor poured

Plantroom wall being built in blockwork

Steels RSJ in place to accept hand cut roofing truss

.

Timbers nearing completion in ready to accept roofing

Tile baton fixings approved

Roof insulations and tile batons as per spec

Service voids break throughs to be agreed for finishes

Moving forward.

  • Complete roofing including insulation and tiling
  • Screeding planned for Saturday 28th Sept
  • Complete wall repairs to 5 Adams rd
  • M&E roof void set out tbc.