Robinson Archives Building - Progress Report week 7.

08 August 2019

Bill McKim Facilities Manager

 

  • Progress good, ahead of schedule possibly 2 weeks.
  • Below ground foul drains installed
  • Water supplies installed
  • Attenuation in place
  • Brick layers setting out
  • Building control, Site visit as requested all Ok
  • Architect visit Alex Howe
  • Southams visit M&E all in place and agreed routes

Below ground foul drain being installed

Backfilling with drains in place

Surface water attenuation tank being installed

Bricklayers on site

Arial Photos of building site

 

Looking ahead at week 7.

Bricklayers.

Groundworkers

Possible start to gable end?